Supply, Design and Engineering of Integrated Control and Safety System for an offshore facility

The location is approximately 100 miles southeast of Lagos and 37 miles west of Warri. The plant processes approx. 680 million standard cubic feet of natural gas per day. The customer had planned a Gas Gathering & Compression Platform and a Non-Associated Gas (NAG) Wellhead Platform in an offshore field for its ongoing flare reduction efforts. INTECH was called for:

  1. Engineering, Design, Fabrication, Integration, Testing, Documentation and Supply of Process Control System (PCS)
  2. Engineering, Design, Fabrication, Integration, Testing, Documentation and Supply of Safety Instrumented System (SIS)
  3. Engineering, Design, Fabrication, Integration, Testing, Documentation and Supply of Fire and Gas System (FGS)
  4. Startup &Commissioning Services

INTECH based on its rich oil & gas domain knowledge, technological expertise and its vendor neutral approach to system design choose hardware that was best fit for customer needs & requirements. The system delivered was designed keeping in view the availability, reliability, international safety, compliance and operational excellence standards specific to a gas processing facility. The hardware selected included:

  1. Process Control System- Allen Bradley Control Logix
  2. Safety Instrumented System – Allen Bradley Control Logix
  3. Fire & Gas System –  Allen Bradley Control Logix
  4. Fire &Gas detectors
  5. Human Machine Interface – Wonderware Intouch
  6. Process Historian – Wonderware

INTECH enables oil & gas facilities to optimally deploy and maintain automation solutions resulting in enhanced productivity, reliability, safety, compliance, and flexibility of the assets and the enterprise. INTECH has completed over 100 major upstream Oil & Gas projects for the top ten E&Ps globally over the past years. INTECH is a vendor neutral automation solutions provider with experience with almost all well-known PCS/PLC.